Work-In-Progress Aging Report

What's the difference between transaction date and accounting date? When I run the WIP Aging Report, there's a large difference when I age the report by the two different dates. 


Posts: 19
Registered: ‎08-17-2009

Re: Work-In-Progress Aging Report

Hi AJenk, Good day! Are you referring to the Unbilled Detail and Aging report. Under the reporting option of this report, you have 3 Aging date options: Select the date from which the aging data is calculated: Today's Date — Age transactions based on the current date. Period End Date — Age transactions based on the last day of the current accounting period. Specific Date — Age transactions based on a date you specify. Enter the date, or click the calendar icon and select the date. If this does not answer you question, I would suggest submitting a support ticket via the Submit Case or Chat options. I hope that helps.